Tuesday, 6 January 2015

Rendering Magnesium Oxide Board

The laundry and second bathroom had been left unrendered as these rooms had tiled floors and did not need to be done for the polished concrete floor to be finished. Further delay was caused as I had not finished the mosaic tiling for the bathroom. With Christmas coming up and more people staying in the house, it was time to finish the second bathroom.

I had been unhappy with the finish of the AHMC render mix on the MgO board walls and the renderers had found it very hard to get the render to stick to the MgO walls. I raised my render on MgO issues with some other hemp builders, sought their assistance and received several suggestions. I had also seen some straight sand lime renders used on strawbale houses and with all this I undertook my own rendering experiments.

Freshly done render tests on MgO Board
I tried three different mixes applied using two different methods. The top row from left to right are (1) standard AHMC hemp render mix, (2) half AHMC hemp render mix half lime/sand mix and (3) straight lime sand. The lime/sand mix replaced the same volume of AHMC render with straight builders lime. The bottom row uses the same mixes but with the addition of a coat of Bondcrete on the MgO board left to go tacky. The Bondcrete did not work at all and in fact it was harder to get the render to adhere to this mix than to the untreated MgO board.

Dry render tests on MgO board

(1) standard AHMC hemp render mix

(2) half AHMC hemp render mix, half sand/lime

(3) sand/lime
 I had a bit of mix (2) and did some extra sections at either end of my test MgO board. I have some disclaimers to this test as firstly I am not a good renderer, secondly the test was carried out on a hot day and thirdly the number (3) mix had too much lime to sand and should have had more sand, the replacement of AHMC mix with straight lime should have been done by weight rather than volume as the AHMC mix had hemp fibres in to which are very light but bulky.

Mix number (1), the standard AHMC mix, was still difficult to adhere to the MgO Board and as on the MgO board the mix can not press into the wall like it can with a hemp wall, the hemp fibres came to the surface and stuck out too much for my liking. Mix number (2), the half AHMC half sand/lime mix was easier to spread and adhere to the MgO Board, it also produced a smoother surface. Mix number (3) the sand/lime, mix cracked badly when  applied at the same thickness as the other mixes and was hard to apply in a single 8-10mm coat. I hoped to be able to get away with using a single coat to save labour and hence cost.

John, my first renderer, came around and looked at the tests. He agreed that the second mix looked best but we agreed to use a little less lime in the sand/lime mix. The mix we used was two bags of 22.35kg of river sand (this had been measured out earlier for the render and we had some measured out bags left over), one 9kg bag of AHMC hemp render mix, half a 9 litre bucket of builders lime (so about 4 1/2 litres) and 160g of yellow oxide (this was double the amount used for a single AHMC mix, since in effect we were making a double mix).

The new double size mix of render was mixed up in our pan mixer (mortar mixer) that we had used to make the wall mixes. Previously we had used a standard cement mixer for the render as out pan mixer was out on loan to another hemp builder. The pan mixer was a bit slower than a cement mixer but did a good job mixing the render and was much less dusty.

The amended render mix adhered to the MgO board much better and easier to move around on the wall. The MgO was still not the greatest substrate to render on but it was now much more achievable. A smoother more consistent finish was also able to be achieved. The only issue was that the walls were a little yellower than expected. I really should have tested the actual mix we used first rather than just relying on my test. I assumed it would be ok as my test used a proportional amount of oxide, but as we now used less lime the colour became more intense. The good thing is that the family liked the more intense colour and it is a nice bright sunny yellow in these small south facing rooms.

Amended render on MgO Board

Rendering the laundry
The bathroom also had one hemp wall. The amended render went on this wall really well. When John started rendering this wall I wondered why he finished so quickly, it was because even with the amended mix it was still much easier to to render a hemp wall than a MgO wall.

The last walls in the bathroom were rendered between Christmas and New Year. It was great to be able to hang the bathroom mirror. When we were building the walls we put an extra nogging in the frame right where the mirror had to be hung and thankfully we remembered where it had to go and the screws hit the nogging.

Bathroom mirror on wall

Freshly rendered bathroom wall
The only disappointing news was that we were one bag of render short and one wall in the laundry is still unrendered. This will be fixed up in  the new year. While disappointing it was better to leave this wall than try and do a too thin coat of render and have it crack or not work well.

Wednesday, 28 May 2014

Significant Progress



Bathroom external wall rendered
Rain chain and more finished walls
Having a renderer that has been able to give some full time attention to the house has led to significant progress being made over the last few weeks. The internal walls are finished and there are only three external walls, three upper walls and a small section around the front door to go.

Freshly rendered back wall
Front of house freshly rendered
The hemp lime rendering  has not been easy. The window headers have been particularly difficult as the render is not very sticky and so tends to fall off the window headers, the render also does not spread very well and so cannot be moved around on the wall, it also tends to get rougher if you go back and try to touch it up.  But Brett, the renderer, persevered and has managed to do the window headers by filling any gaps or holes first (particularly any patches where chunks of the hemp wall have broken away or crumbled), then when this is dry he has attached a straight edge to the window and finished the underside of the window header, then when this has gone off a bit he has gone back and done around the face of the window header. The window headers have been done the day before the wall has been rendered. Then when the wall is done the sides of the windows or doors have been done first followed by the face of the wall. 

Patching the worst of the holes in the window header
Window header rendered
 The walls were wetted down before being rendered, then sprayed with a light mist of water on the evening after the wall was done on warmer days or the next day, to slow the drying down.
The hemp render was not suitable for use on the Magnesium Oxide (MgO) board at all. It had to be done in two coats, increasing the cost. The MgO wall could not be wet down first otherwise the render just slid off. Even then the render had great trouble sticking to the wall and if done too thickly would bubble and fall off or crack and just slide. The last MgO walls were done by splattering the first coat on which seemed to work better, but it was a bit late in the project to worth this out.  The second coat of render on the MgO was very difficult to work and on most walls the finish was very patchy both in texture and colour.

Left - Hemp render on MgO Board and right- hemp wall
Hemp render on MgO Board
With only a few walls left to do the render will be finished in a few weeks after Brett takes a break from the hemp walls, with a few more conventional jobs. The completion of the internal walls and the external walls, that have lights on them (thank you Brett for doing those walls at short notice), meant that the electrics in the house could be finished. Paul and Luke from Solar Connections came down and fitted all the internal and external wall lights and got all the power points working. A small problem arose when the back circuit and stove circuit would not work. I panicked that there may be a problem with the wiring in the wall or roof and I would have to start pulling the ceiling down to find it. Thankfully this was not required, but a mix up of the stove and dishwasher power points will hopefully be resolved by long cords on these appliances or a short extension cord hidden under the cupboards.

External light installed
Front of house with external lights installed
 I had forgotten about the LED lights under the overhead kitchen cupboards and so spent much of the day putting up the cupboards so the electricians could install the lights. The LED lights were made up to fit the length of the cupboards, leaving a gap for the range hood over the stove.  

Kitchen cupboards and LED lights underneath
Everything happened at once as on the same day the electrics went in, Brett was rendering the external walls and Greg from Alpine Glass put the semi frame less shower screen in the front bathroom. Plus he helped me out by drilling the holes in the tiles for my toilet roll holder, I had been scared to do these for fear of cracking the tiles. With the right drill bit and experience it was no problem.

Semi frame less shower screen
Toilet roll holder
The completion of the internal rendering meant that the final finish on the floor could be done. Before this could be done I had to remove all the boards and plastic protecting the floor and remove the tape and clean the excess render from around the edges of the walls. I used vinegar and hard work to clean up the render from the edge of the floors and had to vacuum and mop the floor several times with multiple changes of water to get rid of all the fine dust. 

Floor in need of more mopping
Cleaned concrete floor
 The first coat of finish on the polished concrete had what looked like crazy paving type pattern cracked in the top of it. This was only visible when light hit the floor at an angle but was much more obvious under artificial light. There were also a few patches of white spots and some rough sections where things had fallen on the floor when the first coat was drying as this was done before the windows had been put in.  

Crazy paving cracks in sealer
White dots on concrete
Henry and Adrian from Dayman Group returned to fix up the floor. It had been two years since they did the first cut on the polished concrete and almost a year since the first sealer went on. The floor was given a light sand which will hopefully resolve the crazy paving cracking and remove the rough sections. A bit more of a sand was required to get out the white spots, which I was told were caused by the floor being covered before the first lot of sealer had fully dried. They also fixed up some patches which would have been covered by the kitchen cupboards, except that the cupboards we are installing are about 30cm off the ground. 

I left while the final coat of floor sealer was still wet and so am keen to get back down there and see what the final finish is like.

Saturday, 21 December 2013

A Spate of Problems



We had been off site for some time when we returned it was clear that something had gone wrong on the most recently rendered walls. The walls were very patchy and had much larger cracks than any of the hairline cracks we had before. The walls were also not as smooth and in parts almost looked pitted. Having put so much work into every aspect of the house I cannot leave those walls as they are, even if it means putting another coat of render on them myself. The only cause I can think of is that the render had too much water in it. As the weather has got warmer the render has been getting more and more water in it and it may have come to a tipping point where this has caused a significant difference in how it has dried and the finished result. We will have to go back and do an area using a less wet mix and see if the finish goes back to that of the earlier walls that were done. The flow on effect is that the rendering of the internal walls will not be finished before Christmas, so the floor will not be able to be completed and we will not be able to live inside. I am disappointed by this, but would much rather a well finished house than some patchy cracked walls just for the sake of a bit of time. 
Patchy render finish
Big cracks and pitted texture to render

Our neighbours are building a large shed and needed to run stormwater from there to the front of their block. They suggested that we connect the overflow from our water tank through their block to the street rather than having to do a pit in the backyard for the stormwater as, due to the slope of the land and that we are a battle axe block, we cannot run our stormwater to the street through our block. I advised our plumber of this and because we did not need to get a pit in the backyard any more I arranged for the excavators to come in and level the block. Our neighbours were advised by Council that they could not just allow the stormwater to go through their block without an easement. This was not an option so now we need to do pit in the backyard again and I have now got my sequencing all wrong by getting the excavators in to do the levels before the plumber put in the stormwater pit. We will also have to try and keep the tank half full so we don’t end up with an overly soggy patch in the backyard every time we get a downpour. 

The first rangehood we bought was larger than the size described in the brochure, so we had to return it, frustratingly the appliance store would only give us an exchange voucher and not a refund. Limited to what was on offer at the appliance store we bought another rangehood. It fitted the cupboard but was slightly higher than the previous one. Cutting out the hemp with a cold chisel to make room for the exhaust for the rangehood was easy until I found that I hit a stud and a noggin. The noggin had been put in so that I was able to hang the kitchen cupboards from the frame. 

I am making the the ducting for the exhaust from the rangehood from 150mm plumbing pipe since I need a 90 degree elbow and otherwise it is a very short run straight out the wall. The pipe just hit the bottom part of the noggin and once side of the stud. Not wanting to reduce the strength of the stud too much I decided to angle the ducting so that I just had to take off the corner of the stud. This was not as easy as it first seemed.

To add to my woes or perhaps because my thinking had been clouded by my woes, in trying to put in the exhaust for the rangehood I drilled through an electrical cable. An electrical cable that ran straight through a stud, with the cable cut halfway through the stud. The cable was for the power point for the rangehood and thankfully the power point circuit was turned off. In my defence the cable looked like it went through lower than it did, but I should have been more careful and consulted the photographs of the frame and wiring like I did when choosing how and where to attach the kitchen cupboards. I went through the now usual method of problem solving: tears, anger, then solution.  I moved the power point. I chipped out a bit more wall until the cut cable was long enough to attach to a power point. I then chased in the longer part of the cable so that it too came out at the same place. A beautiful solution, except that the power point is now on the opposite side of the rangehood to the power cord, but it will all be inside a cupboard so no one will see this. 
 
Cut power cord

Duct hole and moved power point

The upset and disappointment of all these disasters was washed away by the hot water of a long shower; the first in the house where the hot water came out of a tap and not a kettle. While we had been off site the plumbers came around and installed the regulator for the gas bottles. We hooked up a barbecue LPG bottle temporarily while we waited for delivery of the full size bottles. The power points for the house are not yet functional so we put an extension cord from the meter box to the instantaneous gas hot water unit and with gas and power connected finally had that true sign of an advanced civilisation – hot water on tap. The Methven Satinjet water saving shower head gave such a luxurious evenly spread flow of water it served to confirm the severe shortcomings of the water saving shower heads we have put up with for the last 10 years. 

Tuesday, 29 October 2013

How to Hemp Lime Render

With well over half of the internal walls rendered, John our renderer has mastered the application of the Australian Hemp Masonry Company hemp lime render. We have put together a little video on the rendering process.



The first room to be completely rendered was the bathroom. In the bathroom the render produced a very nice finish that ended flush with the tiles, each being about 10mm thick. The main kitchen living area was the second room to be completed. Two of the bedrooms are not far off completion with only the second coat on the Magnesium Oxide board to go. Even the third bedroom now has one wall rendered. All the hemp walls have been rendered in a single 10mm coat. The MgO board walls have been rendered in two approximately 5mm coats.

Last wall in the main room freshly rendered



Main room rendered
First wall started in the last room to be rendered


Friday, 12 July 2013

Solar Connected

We entered into a contract with Solar Connections and the solar panels went on the roof on July 2012, however at this time we had no walls, only the timber frame so Paul from Solar Connections had nothing to attach the inverter to. The walls were completed in February 2013, but we wanted to render the walls first before the inverter went on. However, we ran out of time as the system had to be fully installed by 30 June 2013 to take advantage of the government incentives that were in place when we entered into the contract for our system, but ended in January 2013. On the first day John did some rendering I got him to do a patch of render on the external wall where the inverter would go. It turned out that the patch of render was only just big enough. On 24 June 2013, with a week to go, Paul put the inverter in and got the solar working. We then needed to get a Level 2 service provider to change the meter over so that we could record the electricity we generated.


Wayne from FAW Electrical, who had originally hooked up the power for us came back and added an extra meter to measure the electricity we export to the grid. Unfortunately we missed out on the government feed in tariffs for solar electricity generation, so we have what they call net metering. This means that if we use electricity we have generated it is not recorded on either meter. If we generate more than we use this is exported to the grid and recorded on the export meter and when we use electricity at night or when we are not generating enough electricity to cover our needs we use electricity from the grid and this is recorded on the normal import meter.  

John the renderer only had half a day to work on the rendering and got one of the internal walls of the front bedroom done. The timber window reveals that has been set 10mm in from the hemp walls provided good render stops  and the avoidance of having to use trim around all the windows gave the simple unfussy look we are after. Rendering down to the slab and up to the ceiling and creating neat edges at these joints was a bit more time consuming.

Wet render

As the wall dried it began to look a bit patchy. this is probably because of the slightly different moisture in the walls making the render dry at a different rate. We are not concerned as we watched this process on the render on the inside of the wardrobe and it dried to an even colour. The week of solid rain that the occurred immediately before the rendering of this wall probably made everything a bit moister than normal.

Partially dry render a week after being done
The wardrobe render was dry but had a wet patch on it probably from the several days of torrential rain the Shoalhaven area had, as the wall just outside this area was one of the few places that the eaves do not cover, this will be solved as thee wall will be covered when the sheeting goes on the awnings. It was hard to work out what colour the render was. In the early morning it looked quite yellow, but in the middle of the day the green plastic covering the rest of the windows in the room created an odd light. We reused the plastic bags the ceiling insulation came in to cover the windows. Although after many weeks of trying to get the right colour for the render, it is clear that the same amount, proportionally, of oxide in the mix has not resulted in the same colour we chose from our tests. It looks like we will just have to be satisfied with the colour we have got.

Windows taped up ready for rendering

Casting an odd green light
Wardrobe rendered
There were big seas in the wake of the winter storms, but watching the waves crash over rocks that normally stand proud of the water was awe inspiring and a great way to wind down after a weekend of building.





Wednesday, 12 June 2013

Hemp Lime Rendering Commenced and Nelligen Studio Revisited


A busy long weekend was spent,  finishing the wardrobe in the front room and putting on the door jamb and inbuilt pelmet for the curtain that will be the wardrobe door. I used Tasmanian Oak timber, as I had for the other door jambs on the house, cut to size to provide a render stop for the 10mm of render on each side of the wall. The ceiling and door jamb was then covered in plastic, reusing the plastic bags the insulation came in, to protect them from the render.

Our friends Martin and Nerida stopped in on an unwintery warm sunny Saturday with their chainsaw  and we cut up some very sizable tree branches that had fallen onto the block over the previous 12 months, most significantly the branch that dented the fence and the other that cut a hole in the back gate. They left with a trailer load of firewood , but not before I had roped Martin in to help me with the battens and valley boards for the awning over the front door. The tricky part with this was that the section of the awning over the front door only has two rafters, one of which is the valley rafter. Because we needed to put the valley boards in next to this rafter we could not attach the battens to it. Instead, we used left over material from the awning rafters to create perpendicular rafters that ran between the two rafters and on top of which we attached the battens. Over the rest of the weekend we finished the battens, valley boards and hip battens for the whole front section of the house. 

Valley boards and battens with extra support installed
Battens and hip batten installed
Being a long weekend we took a trip down to Nelligen to help our friend Nicole with her hemp walled studio. She had made good progress since we had last been on site. We spent the day helping her build the hemp walls along he south wall and above the stone foundation wall. The east wall above the stone foundation was originally to be made of stone but a change of plans after the frame was made meant that adaptations had to be made to change the originally 500mm walls to be partly 300mm and 500mm. The thicker walls used up the hemp very quickly.

Stone foundation wall and formwork for hemping

The west and part of the south wall are completed up to door height.

West wall
West and south walls
With all the different spacer sizes she was using, Nicole abandoned the use of spacers and instead used a level to ensure the formwork went up vertical from the lower measured section of the wall.

Formwork being filled with hemp
Sheet bracing filled on both sides
Permanent formwork around windows
Nicole's hemp came from two different sources. The first sections of wall used hemp from Ashford and the current sections she is making use hemp from the Hunter Valley. Although I also sourced my hemp from Ecofibre in the Hunter Valley it was very different from the hemp Nicole was now using. Her hemp came in compressed bales and was much finer than the hemp I got from the Hunter Valley and was even finer that the hemp from Ashford. Having worked with all three different chops of hemp, my current preference is for the chop from Ashford. The larger pieces of hemp from the Hunter Valley did not interlock as well as the finer chop, but the very fine chop from the Hunter Valley appeared to compress so much together that the walls seemed quite dense. The Ashford hemp seemed to be a balance between the two. However, I will reserve my final judgement until Nicole's walls are thoroughly dry and the properties of the walls using the different hemp can be better observed.
Compressed bale of Hunter Valley hemp
Wall using Ashford hemp
Wall using Hunter Valley hemp
Hunter Valley finer chop of hemp
Nicole loaned us he old cement mixer for our rendering and John the renderer came around to try out the hemp lime mix. John made up the mix a bit runnier that I had done the test samples, but that may explain why I had some difficulty applying the render on my test samples.

Hemp lime render being mixed
Render ready to go on the wall
Self adhesive fibreglass mesh was applied to the joints between the hemp and MgO boards.
 John first tried out the render on the inside of one of the wardrobes, the top section of which was a very awkward area to access. Perhaps this was not the best place to start, but it was an easy place to hide any mistakes that were made. John found the hemp lime render different to any other product he had used. He found that it was best to put the render on at as closest to the final thickness as possible, float it and them leave it. Floating the render again later, as is done with cement render just brought up the grains of sand and made the finish less smooth. Unexpectedly the render did not cover anywhere near the 5sqm advised by the manufacturer. When we next do a larger section of wall we will more accurately measure the square meterage covered by each bag of render. John was able to get the finish we wanted to achieve, a consistent but not completely flat finish, just like a traditional lime rendered building.

Render mesh applied to joints
Rendering the inside of the wardrobe
Awkward top section of the wardrobe
We need to get the inverter for our solar panels installed by 30 June, to take advantage of the government rebates that were in palace when the panels were first installed. So, John did a patch of render where the inverter will be placed. John was unsure of the best way to render the MgO boards and whether the render worked better with or without render mesh so he did some tests, doing a 10mm coat of render mesh, a skim coat on render mesh and the same again 10mm coat and skim coat without render mesh. The skim coat is a thin coat that is later covered with the finish coat of render. When dry we will be able to see which method provides the best adhesion.

Render patch for solar inverter
Skim coat and 10mm coat on render mesh
Top to bottom; skim coat no mesh, 10mm coat, skim coat with mesh, 10mm coat with mesh all on MgO board